The City is working to advance designs to implement intersection improvements at three locations in Beverly, including:
- Rantoul Street, Cabot Street, Water Street
- Balch Street, McKay Street
- 1A, County Way, Route 97 (Henry’s Intersection)
Recent Updates:
Construction for Traffic Improvements at the Three Intersections will resume this Spring 2022
May 16-20: Location 1
- Continued curbing and sidewalk work
May 12-13: NIGHT WORK at Location 1
- Paving binder from 8PM - 5AM
May 9-11: Location 1
May 8: NIGHT WORK at Location 1
May 4-6: Location 1, 2 & 3
- Location 1 installing curb and pouring sidewalks
April 25 - 29: Location 1
- Curb and sidewalk installation on Water Street
April 19 - 22: Location 1
- Curb and sidewalk installation on the right side of Cabot St (starting at the bridge)
April 14- 19: Location 1
- Remove islands and full depth paving
April 10 - April 16: Location 1 and 3
- Curb and excavation work at Location 1
- Concrete sidewalk poured at Location 3
April 3 - April 9: Location 1
- Light pole foundation installation
- Catch basin clean out
March 28 - April 2: Location 3
Construction of Island on Dodge St
Curb installation at Fire station
Concrete driveway for Fire station
Find additional information on the Massachusetts Department of Transportation project page.