Street Paving

follow twitter@BeverlyEngineer


2019 Current Paving Projects

Baker Ave (Odell-Pickett)/Boyden/Giddings/Lefavour/Clark/Whitney/Sargent (Peabody-Clark) – Street Paving (Grind and Overlay) – COMPLETED
Cabot Street (Pond Street – Abbott Street) – Complete Street Restoration
Chapman St (Sidewalks/Parking Lot Federal Street – Bow Street) – COMPLETED
Colon St Sidewalk (Spring Street – Heather Street) – COMPLETED
Dodge St (Morningside to Laurel) – Sidewalks and Road Resurfacing – 
COMPLETED 
Lothrop St (Wilson Avenue – Ives Street) – Road Resurfacing – COMPLETED
Odell Ave (Pickett Street – Baker Avenue) – Sidewalks and Road Resurfacing – COMPLETED
Parsons Dr (All) – Drainage Improvements/Sidewalks/Road Resurfacing
Smithson Dr (All) – Drainage Improvements/Sidewalks/Road Resurfacing
Woodland Ave (Greene St to Livingstone Ave) – Sidewalks/Curbing
Crack sealing – Various Streets in 2019 COMPLETED

 It is important to note that there is No Exact Schedule or Timeline. During sidewalk construction, it is possible that trees may need to be replaced. Please check this website frequently for Paving Related Updates (below). Follow us on Twitter @BeverlyEngineer 


PAVING RELATED UPDATES

***12/6/19 UPDATE***

Cabot St – The sidewalk contractor will be back in the Spring of 2020 to start the sidewalk work on the even side of the road. Link to project website here.

Smithson Dr/Parsons Dr – The sidewalk contractor is working on driveway aprons, installing berm, granite curbing and handicap ramps. Final pavement is currently scheduled for the end of next week. The rest of the sidewalk work will be complete after final pavement weather permitting this winter. If not it will be completed in the spring of 2020.

Dodge St – The sidewalk contractor has to finish loaming and seeding and punch list items.

Woodland Ave – The sidewalk contractor should begin the week of December 9th. Curbing will be reset and new concrete sidewalks will be installed.

**During paving operations it is critical to the success of the project that all vehicles are off the road by 7:00am or they will be towed. Police details, City of Beverly personnel, and the Contractor Crew will be able to assist you during this process.**


 ***Important Information for those Residents affected by the Street Paving Projects***

Upon completion of the paving projects, the newly paved streets will not be permitted to be dug/opened for FIVE years (IF approved by the Engineering Department). Therefore, if there is any pending underground utility work to be performed it must be completed prior to completion of the paving project.

Examples of Underground Utility work are but not limited to:

  • Electric
  • Cable
  • Sewer (chronic issues should be addressed at this time and should be brought to the attention of the Engineering Department 978.605.2358)
  • Water (volume, pressure, and quality issues should be brought to the attention of the Water Department at this time 978.921.6057)
  • Natural Gas: In the event you do not have natural gas service and are interested in changing to natural gas, we would suggest that you contact National Grid (1-800-233-5325) to schedule your service at this time. Please notify the Engineering Department if you need assistance you with expediting your request (978.605.2358).
  • Sump Pump: If you have a sump pump it may be possible to connect to the City’s drainage infrastructure. Call the Engineering Department if you need assistance with this matter (978.605.2358).

The Engineering Department is available to assist you with any questions or concerns you have. We will also be updating this important project with information that can be found on this link as it becomes available.